What do the different split reasons mean?

34 views 0

  • Material Shortage – shortage of stock materials (such as masking materials) to enable ompletion of entire order quantity

 

  • Capacity Restriction –  Production did not have the capacity to complete the full order quantity

 

  • Part Batch Return from Subcon – Only part of a batch was returned from subcontractor so only that quantity can be completed

 

  • EBQ – Production processed an economic Batch Quantity rather than the complete order quantity

 

  • Partial Delivery – Only a part of the order is to be delivered – usually at customer’s request

 

  • Internal Reject – Some parts of an Order have been rejected so only the remainder can be completed

 

  • Lost Items – Some parts of an order have been lost so only the remainder can be completed

 

  • Return Subcon – Part of an order that has come back from Subcon has been rejected and has had to be returned to the subbcontractor for rework

Was this helpful?

Yes  No
Related Articles
  • RFQ Bundling options
  • Navigation Bars
  • How do I reprint a credit note?
  • How do I print a credit note?
  • How do I change credit note details?
  • How do I create a credit note?
Split Job
  • What do the different split reasons mean?
  • How do internal rejects prompt a split?
  • Do I need to process / print split job jobcards?
  • When are jobs added to the Split Job list?
  • How do I split a job?
  • Why would I need to split a job?
Sitemap
  • Release notes
  • Knowledge Base
  • Request Support
Find Us

Fusion Hive, North Shore Innovation Centre, North Shore Road, Stockton on Tees, TS18 2NB

Search
  • Privacy Policy
  • Terms of Use
Popular Search: