Navigate to Network⇒Production⇒Job

 

Select the job whose progress is to be recorded by double clicking it and then select the Progress tab

A list of the operations for the selected job is then displayed – select the operation to be progressed and click Add Progress

Note – You can only add progress to an operation if the previous operation has been completed

Note – If the add progress button is not allowing you to press it then you have to print the job card first: then it will let you

 

In the pop-up box, enter the Start Date/Time and Finish Date/Time and whether any parts have been rejected and then click OK

Note – The Finish Date/Time must be later than the Start Date/Time otherwise an error message will appear and the Finish Date/Time will need to be amended

 

The Time Spent on this operation will now show, the Ops Completed field will state Yes and the Traffic light will change to green

In the lower half of the screen, details of the Start and Finish Date/Times and the Operator(s) who have started and finished the operation will appear. The total time spent on the job for all of the completed operations will also be displayed

 

Repeat the above instructions for any further completed operations and then click Save followed by Close

Was this helpful?

Yes  No
Related Articles
  • RFQ Bundling options
  • Navigation Bars
  • How do I reprint a credit note?
  • How do I print a credit note?
  • How do I change credit note details?
  • How do I create a credit note?
Production
  • I don’t have shop floor data capture, how can job progress be recorded?
  • How do I see WIP for a particular customer / order number?
  • What does the WIP list screen show?
  • How can I clock an operator off operations?
  • How can I see WIP for a particular operator?
  • How can I see WIP for a particular operation?
  • What does the active jobs screen show?
  • What happens if a job fails a test?
  • How do I record test results against a job?
  • How do I add a required test to a job?
  • What is Test results used for?
View All 55  
Sitemap
  • Release notes
  • Knowledge Base
  • Request Support
Find Us

Fusion Hive, North Shore Innovation Centre, North Shore Road, Stockton on Tees, TS18 2NB

Search
  • Privacy Policy
  • Terms of Use
Popular Search: